This page will inform activities within the project management strand (as mapped onto "DeFT jobs" discussed at the 16 March team meeting)
Themes/ work strands |
Tasks involved |
Key Milestones |
Persons responsible* |
Comments/issues |
8. Project management |
1. Manage DeFT Project
|
31 Mar: Contracts sent off to technical partners. Schools to sign contracts sent at beginning of March 20 Apr: Interim Report to JISC 30 Aug: First version report from evaluator ready for inclusion into final report 17 Sep: Draft final report to JISC 30 Sep: Final version of summative report from evaluator 19 Oct: Final and completion report to JISC |
AG with NW's support |
While evaluation is an ongoing element of the project and we have an evaluator who acts as a critical friend, she will also need to produce a summative report for inclusion into final report for JISC |